Sheridan Avenue Construction Meeting on February 13th

Everyone is invited to an important meeting on the Sheridan Avenue Project.

The public meeting will begin at 6:30 p.m. on Thursday, Feb. 13, in the Cody Auditorium. The meeting will be hosted by S& S Builders of Gillette, the prime contractor awarded the bid for the project, and the Wyoming Department of Transportation. This meeting is a few weeks out from the commencement on the Sheridan Avenue/10th Street intersection on March 2nd – as long as the weather allows it.

While this meeting will cover the overall scope of the project, weekly public work progress meetings will be held at 10 a.m. every Tuesday between March 3 and June 9 at the Cody Club Room throughout the duration of the project. Each meeting will present a two-week layout for construction.

There have been alterations to the time table for the project:

— Phase I was changed (from complete all work from 10th Street to 15th Street by June 15, 2020) to complete all work from 10th Street to 14th Street in the same time frame.

— Phase II was changed (from complete all work from 15th Street to Alger Avenue after Aug. 24, 2020 prior to winter shut down) to complete all work from 14th Street to Alger Avenue through concrete grinding and texturing prior to 2020 winter shut down.

— Phase III was changed (from complete all remaining work prior to June 15, 2020) to complete all remaining work except resealing joints and pavement markings on Phase II and Phase III prior to June 15, 2021.

— Phase IV was added from Aug. 24, 2021, to Sept. 30, 2021, to complete all remaining sealing of joints and pavement markings.